[env-trinity] Change Order - Lewiston Dam - UPDATED
Huntt DeCarlo, Caryn
chunttdecarlo at usbr.gov
Sun Jul 29 13:48:15 PDT 2018
On Sun, Jul 29, 2018 at 1:30 PM, Thomas Patton <tpatton at usbr.gov> wrote:
> Please maintain release to Trinity River at 800 cfs.
>
> On Jul 29, 2018, at 8:24 AM, Thomas Patton <tpatton at usbr.gov> wrote:
>
> Project: Lewiston Dam
>
>
> Please make the following release changes to the Trinity River:
>
>
>
> Date Time From (cfs) To (cfs)
>
> 07/29/2018 0800 1250 800
>
> 07/29/2018 0900 800 450
>
>
> Comment: Emergency release due to power shutdown and fire activity.
> Expect possible reservoir and river release fluctuations.
> Issued by: Tom Patton
>
>
> On Jul 28, 2018, at 5:22 PM, Thomas Patton <tpatton at usbr.gov> wrote:
>
> Project: Lewiston Dam
>
>
> Please make the following release changes to the Trinity River:
>
>
>
> Date Time From (cfs) To (cfs)
>
> 07/28/2018 1730 750 1250
>
>
> Comment: Emergency release due to power shutdown and fire activity.
> Expect possible reservoir and river release fluctuations.
> Issued by: Tom Patton
>
>
> On Jul 28, 2018, at 3:39 PM, Thomas Patton <tpatton at usbr.gov> wrote:
>
>
> Due to the fire activity, Trinity Dam became isolated from the power
> network and continues to serve a local area of power for safety purposes.
> Spring Creek and Carr power plants are currently down. As a result,
> Lewiston water elevations were managed by emergency increased releases from
> Lewiston Dam and Carr Bypass. Over Friday night, Lewiston Lake reservoir
> rose higher than the normal operating range which resulted in an increase
> in release from the Trinity River to about 1,100 cfs. River releases are
> coming down today but are still higher than what was noted yesterday.
> Please take extra precautions due to varying releases on the Trinity River.
> We are trying to reduce the lake levels but expect this will be difficult
> due to the facility communication issues and power generation situation.
> Low lying areas surrounding the lake and marinas at Lewiston Lake are
> expected to be affected by the higher and variable lake levels.
> Reclamation managed to get Lewiston Dam releases to the Trinity River down
> to about 750 cfs by 3:00 pm Saturday afternoon and will remain at this
> level until further notice.
>
>
> Issued by: Tom Patton
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://www2.dcn.org/pipermail/env-trinity/attachments/20180729/e8de9976/attachment.html>
More information about the env-trinity
mailing list