[1st-mile-nm] Windstream NM Stimulus Update
Richard Lowenberg
rl at 1st-mile.com
Tue Feb 7 13:48:38 PST 2012
Exerpted from a longer article, below are a couple of lines about
Windstream’s broadband stimulus funded efforts in NM. Click on the
link below for the complete article.
Windstream and TDS Execs Provide Stimulus Update
http://www.telecompetitor.com/windstream-tds-execs-provide-stimulus-update/
Windstream won grants from the Rural Utilities Service totaling $181.3
million for a total of 16 broadband stimulus projects in 13 states. The
grants cover 75% of the cost of installing broadband, with Windstream
investing the remaining 25%, a total of $60.4 million. The carrier is
essentially filling in pockets within its existing territory that
currently lack broadband.
(snip)
The states where Windstream has the most work left to do are New
Mexico, where the company just gained a long-pending environmental
approval, and Kentucky, where the company is still awaiting
environmental approvals in a couple of individual markets.
Engineers already have staked routes for 90% to 95% of the 5,400 route
miles included in Windstream’s winnings. Accordingly construction should
be able to start next week or the week after in the newly-approved areas
in New Mexico.
(snip)
--
Richard Lowenberg
1st-Mile Institute
Box 8001, Santa Fe, NM 87504
505-989-9110 / 505-603-5200
www.1st-mile.com
rl at 1st-mile.com